Project Size:
$7.5 million
Completed: April 2010
.................................................
Annual Energy Savings: $409,283
Reduction in Energy Costs: 27%
.................................................
After a thorough inspection of Scarsdale UFSD’s
facilities as part of the Building Condition Survey process, ECG’s engineers
noted that the district had several systems that could be upgraded through an
Energy Performance Contract (EPC).
ECG was subsequently retained to assist the district through
the EPC RFP process. The result was over $7 million worth
of capital upgrades that will be implemented without taxpayer
impact.
Project Highlights
- lighting system upgrades
- occupancy sensors
- integrated building energy management system
- boiler controllers
- steam trap replacement
- thermostatic radiator valve installation
- transformer replacement
- window replacements
- heat-rejecting window film
- vending machine controls
|