Project Size: $17.2 Million
Completion Status- Est. Summer 2013
.................................................
Annual
Energy Savings: $965,482
Reduction in Energy Costs: 37.1%
.................................................
Project Description:
Although the Commack School District had maintained and improved its facilities consistently over the years, many energy consuming systems, such as lighting and energy management systems, had not been upgraded. As a result, a large energy savings opportunity existed, which enabled the District to receive over $17 million worth of facility improvements and a large annual positive cash flow. Commack School District’s Energy Performance Contract will bring state-of-the-art, efficient systems to the District, reducing its current energy spend by 37%.
Project Highlights
- lighting system upgrades
- lighting controls - occupancy sensors
- weatherization
- energy management system upgrades
- steam pipe and valve insulation
- boiler controllers
- roof replacement
- window/door/panel replacements
- window film
- computer power management
- kitchen hood control
- transformer replacement
- high efficiency/variable frequency drives
- boiler/burner replacements
- rooftop AHU/condenser unit replacement
- chiller replacement
- summertime DHW heater
- cogeneration
- compressed air system refurb.
- hot water conserving faucets
- walk-in freezer controllers
- walk-in freezer refurb./replacement
- unit ventilators refurb./replacement
- solar wall ceiling replacements
Back